The City of Holland is backing out of plans for a potential wind farm. The city-owned utility bought the option to lease hundreds of acres in Allegan County after the state identified the area as one of the best in Michigan for wind energy potential.
But after more than a year of serious study, the city doesn’t think there’s enough potential to build the wind farm.
“When we went into this, everything looked like it was going to be a good project to pursue,” said Dan Nally, who directs business services for Holland’s Board of Public Works.
"We shouldn’t take the fact that this project doesn’t go forward that we are not supporting renewable, because we absolutely, positively are. But we will also, at the same time, get the best value that we can,” Nally said.
The wind was good, but not as strong as they had hoped. The plan was to have a 20 mega-watt wind farm-- relatively small compared to large scale commercial projects.
Nally says the utility has spent roughly $678,000 to collect wind data and study the impact on birds, bats and wetlands.
"We don’t feel that any of this money has been wasted. It’s been an investment in understanding what we could and could not do,” Nally said.
Nally says Holland is working on agreements to purchase renewable power from other wind farms, but he declined to give details until any agreement is negotiated.
Holland and all other utilities in Michigan must have 10 percent of their energy come from renewable sources like wind by 2015. Nally says Holland is still on track to meet that requirement.